Steel Conquers the Barito River

29 July 2001

The longest in Indonesia, at over 1km in length, the Barito River bridge is an excellent example of Australian ingenuity and industry capability. Spanning the wide Barito river, it forms a link between Banjarmasin and central Kalimantan. Replacing a car ferry, the bridge carries the Trans Kalimantan highway, a major road artery 2,800km long which connects all areas of Kalimantan.

Location:

Barito River, Between Banjarmasin and Kalimantan

Country:

Indonesia

Project Size:

1,850 tonnes of steelwork

Client:

Public Works Department Indonesia

Engineer:

McMillan, Britton & Kell and Superstructures Engineering

Fabricator:

Transfield Fabrication - Seven Hills
Barito River Bridge, Indonesia, where steel has been used to maximum advantage and techniques have been employed to facilitate speed and safety in construction.


The longest in Indonesia, at over 1km in length, the Barito River bridge is an excellent example of Australian ingenuity and industry capability. Spanning the wide Barito river, it forms a link between Banjarmasin and central Kalimantan. Replacing a car ferry, the bridge carries the Trans Kalimantan highway, a major road artery 2,800km long which connects all areas of Kalimantan.

The bridge provides an excellent study in steel construction. The drive to minimise costs made steel a winner for this project. Steel has been used to maximum advantage and techniques have been employed to facilitate speed and safety in construction. All this has been achieved in remote and difficult terrain and with a labour force relatively inexperienced in sophisticated construction. A large quantity of steel was needed to complete the bridge - the total weight of fabricated steelwork for the project was 2,500 tonnes with the majority of steel (1,850 tonnes) being supplied by BlueScope Steel.

Transfield Construction was awarded the contract for the design and detailing of the bridge, supply of all superstructure steelwork and provision of site advisers to oversee construction. McMillan, Britton and Kell (MBK), in association with Engineering Superstructures (Sydney), were involved in all phases of the design. Austress Freyssinet carried out the cable erection, lifting of truss segments and hanger adjustment. The main contractor for site construction was the State owned PT Adhi Karya.

Design Features

The main criteria for the bridge project set by the client, the Direktorat Jenderal Bina Marga (Public Works Department) were for an economical, yet aesthetically pleasing design which still allowed adequate clearance for shipping traffic.

The chosen solution comprises two suspension bridges end-to-end, each 420m in length, with approach spans totalling 181m on the Banjarmasin side and 60m on the Kalteng side. Each suspension bridge comprises a central 240m span and flanking spans of around 90m each.

The challenge facing MBK design consultants was to design a sophisticated structure which could be built safely and economically by the local contractors who had little experience with large bridges of this type.

Superstructure

The bridge comprises two 3.5m traffic lanes and 1.5m footways on each side. The width between cables is approximately 12m.

Barito River Bridge, Indonesia, where steel has been used to maximum advantage and techniques have been employed to facilitate speed and safety in construction.

A key feature of the design is the dual, asymmetric cable arrangement which provides a 70% increase in bridge stiffness when compared to a conventional, single cable arrangement.

This arrangement, championed by Professor Max Irvine of Engineering Superstructures, resulted in a 40% saving in steel in the towers and deck truss.

The galvanised stiffening truss is suspended from the main cables and supports the roadway and footways. Construction of this space frame was simplified by use of standardised, bolted truss connections.

The deck is also simple in construction, being a composite concrete deck cast in place on permanent steel formwork. The composite action between the deck and the truss results in significant increases in strength and stiffness. The stiffening truss is supported on pot bearings.

Substructures

The concrete abutments and pile caps are supported by 600 and 1015mm diameter steel tube piles filled with concrete and reinforced in the upper section to permit a moment connection to the pile cap.

Towers

Made of steel, the towers are supported on reinforced concrete pedestals built off the pile caps. Each tower consists of two main box-section columns interconnected with tubular cross bracing and catwalk beams which join the columns at the top. Economical in design, the box section of each column is formed by four steel tubes 600mm in diameter and filled with reinforced concrete which acts compositely with the tubes. The tubes are interconnected by 10mm thick plates.

Suspension Cables

Each of the two suspension bridges has four suspension cables, each cable comprising seven individual 64mm diameter strands, bundled together to form a 200mm diameter cable. At Centre Pier B, the draped cables from both bridges connect to a fabricated connection assembly which is stressed to the substructure. At the tops of the towers, the cables are supported by, and clamped to saddles bolted to the tops of the towers. The stiffening truss is suspended from the cables by cast steel cable clamps and hangers at each node point. Hanger rods consist of one or more lengths of 38mm diameter high tensile bars joined together with threaded couplers.

Deck

Barito River Bridge, Indonesia, where steel has been used to maximum advantage and techniques have been employed to facilitate speed and safety in construction.

The deck slab is cast on custom made corrugated steel decking panels which act as permanent formwork. Slotted holes were pre-punched in the decking to accommodate the studs. The 190mm thick slab acts compositely with the steel stringers with both elements acting as part of the truss "top chord". Precast units each side form footways 650mm above the roadway level.

Tower Erection

The columns were supplied in 16m long sections. The first stage of erection involved the complete preassembly of each tower on the ground and the welding together of the two sections of each column. Weighing 30 tonnes each, the columns were erected using a 200 tonne crane, with the bracing and catwalk beams then erected separately, assisted by a second crane with a man box for access. This method of assembly avoided the need for scaffolding and ensured accurate pre-assembly on the ground prior to welding.

Erection of Cables

Strands were erected individually using specialized equipment. Each strand was hauled out from a cable reel behind the outer anchorages, through the outer anchorage tubes, over sheaves at the two towers and through the anchorage fittings at Centre Pier B. The strands were pulled by a 10 tonne outhaul winch at Centre Pier B.

Cable clamps and hanger rods were installed with cranes, using specially designed C-Hook man boxes. An average of one clamp was erected every half hour as erection proceeded on a two shift, round the clock operation.

Lifting of the Stiffening Truss

The stiffening truss components were sub-assembled in the workshop in 12m lengths. The sub-assemblies were then joined together into erection segments 50 - 60m long below their final position or on barges ready for floating into position and lifting. All segments were surveyed for precamber and straightness before bolt tensioning. Bolts were tensioned with impact guns using load indicating washers for tension control. Corrugated steel sheeting covering the entire width of the bridge was also installed during assembly.

Barito River Bridge, Indonesia, where steel has been used to maximum advantage and techniques have been employed to facilitate speed and safety in construction.

After erection of cables and clamps, each stiffening truss segment was lifted into position at four points by four hydraulic climbing jacks acting on strands. Segments weighed between 100 and 138 tonnes.

After lifting all truss segments the hanger bars were installed and adjusted to pre-determined lengths to bring the segments into alignment. The truss segments were then interconnected. The truss was cambered upwards by controlled adjustment of hangers before the deck was cast and the precast footway units installed. A final set of hanger adjustments brought the deck to the final level.

Richard Woods, an associate director at MBK and leader of the design team said: "The extensive use of steel on this bridge allowed rapid, safe construction in difficult conditions. The most complex and technically demanding work was done off-site enabling simple, safe assembly on site to suit the skills of the workforce. With the poor founding conditions, including soft silts and peat layers in the upper 20 metres, the lighter structure led to significant savings in the foundations".

This bridge is an excellent example of clever and practical Australian engineering. The close co-operation among the project participants from the outset ensured the successful realisation of this landmark structure in difficult conditions.

 
Steel In Touch Newsletter

SUBSCRIBE

Our newsletter is packed full of innovative case studies, technical expertise, state-of-the-industry updates and insights from industry leaders.

XLERPLATE® Steel In Touch has become a must-read publication, keeping subscribers up to date with industry news and developments.

Did you know?

Be confident you are buying a trusted quality product